September 2018
At the September 13, 2018, School Board Work Session, Mr. Anthony Colestock from Crabtree, Rohrbaugh & Associates provided a bid summary and an update on the construction timeline for the Middle School Construction project.
Project Schedule
Bid Schedule - North Site Project |
|
---|---|
September 13, 2018 | Board Review of Building CD Phase |
September 20, 2018 | Board Approval of Building CD Phase: Release of Bids |
September 21, 2018 | Bid Release for Building Construction (5 week bid period) |
October 30, 2018 | Bid Opening |
November 8, 2018 | Board Review of Bids |
November 15, 2018 | Board Approval: Award of Contract |
December 2018 | Issue Notice to Proceed |
April 2019 | Building Pad Turnover: Contractors Mobilize On-Site |
July 2021 | Building Substantial Completion |
Return to Table of Contents
Project estimate
Construction Estimate | CRA 100% SD |
CRA 90% CD |
Reynolds 90% CD |
1. Building Estimate | $47,460,219 | $46,223,200 | $48,637,113 |
2. Site Costs | $5,950,000 | $7,483,031 | $7,483,031 |
3. Contingency, Permits, Testing & Inspections |
$3,713,424 | $3,031,776 | $3,031,776 |
4. Asbestos Abatement | $862,736 | $331,690 | $331,690 |
Construction Subtotal | $57,896,379 | $57,069,697 | $59,483,610 |
Soft Costs | |||
5. Basic Services, F.F.&E., Financing, Clerk of the Works |
$6,923,621 | $6,907,642 | $6,907,642 |
TOTAL COSTS | $64,910,000 | $63,977,339 | $66,391,252 |