December 2020
At the December 2020 School Board of Directors Work Session, Mr. Jay Darkey, Construction Project Manager, provided a design update on the Middle School construction project to the school board.
Table of Contents Schedule Update
Areas Completed by May 15, 2021
- Classroom Wings D, E & F
- Kitchen/Food Court
- Administration Office
- Black Box/Music/Band
- Gym/Fitness/Locker Rooms
- Kitchen/Serving
- Area C (Cafeteria)
- Mechanical Room
- Auction for Existing Furnishings
- Relocate/Move Salvageable Items
- Set-Up/Install New Furnishings
- First Day of School in the New Facility!
- May 2021 – loading Dock and Sidewalks Complete
- July 2021 - Asbestos Abatement of Existing School Complete
- October 2021 – Existing Middle School Demolished
- March 2022 – New parking Areas Complete
- May 2022 – Landscaping Complete
- August 2022 – New Bus Loop & Stormwater Basins Complete
Return to Table of Contents
Time to Build Some Excitement!
Working with Administration for Potential
Student Events & Activities:
Student Events & Activities:
- February 2021 – Incoming 7th & 8th grade representatives tour the building for class presentations
- April-May 2021 – Current 6th & 7th grade classes tour the building
- Classes to sign beams during tours (Location to be determined)
- Student committee established to create a time capsule to install in the new building
- Student competition to name the courtyard
- Student class tee-shirt design competition (shirts to be handed out on the first day of school)
- High School engineering class to study the stormwater basin design and prepare a presentation